Schedule
updated 05-19-2002
| Apr 29 | Met with Lars Stanley, discuss project, initial site visit |
| May 9 | Informal Site Exploration, Spent Night in Ft Benchley |
| May 14 | 7:30pm - Benchley 3 Meet, discuss tentative surveying date |
| May 16 | Contact RSC regarding survey equip |
| May 19 | Jon and Perch clear brushies for clear site lines |
| May 20 | Survey site, Clear Vegetation |
| May 20-26 | Build site model |
| May 25 | Initial design ideas put down on paper |
| May 27 | Site Work: Consolidated Brush, Catalogued existing materials |
| May 28 | Summer Classes Begin |
| May 29-June 1 | Continued research, design development |
| June 1-June 3 | Stay out at site, intense design development, masonry experimentation |
| June 10 | Begin addition model for site model, further design development |
| June 12 | Continue model work, begin discussing connections and other detail work |
| June 13 | Homemade bricks done curing, test to see if they're any good. Begin organizing presentation drawings and continue design of connections, structural elements, wall sections, roof framing |
| June 14 | Begin contacting potential straw suppliers |
| June 18 | Continue development and produce presentation drawings of wall sections. |
| June 19 | Research connection hardware during day, continue development and produce presentation drawings of plans (roofing, floor, performance) and connections/ |
| June 20 | Final Topo Drawing |
| June 21 | Tying up loose ends |
| June 22 | Meet with Lars Stanley, present/discuss design |
| June 26 | Meeting to discuss materials/tools needed for footing pouring |
| June 28 | Lars Stanley to visit Benchley site, initial layout of batter boards. Un-official first day of construction. |
| June 29-July 6 | Excavation of footings, preparation of steel reinfocement |
| July 7 | Primary phase of pouring of footings (Pads) |
| July 17 | Fire-pit excavation |
| July 22 | Final Preparations for Second stage of pouring |
| July 23 | Primary CAD of floor framing details |
| July 28 | Second phase of pouring of footings (Piers/Firepit Slab) |
| July 30-Aug 3 | Research pros/cons of potential beam materials (steel, treated 2x8s, engineered lumber); Calculate design loads for steel members; Update CAD floor details; Finalize straw bale supplier |
| Aug 4-26 | Floor Floor Floor when not Rain Rain Raining |
| Aug 27 | TAMU Fall Semester Begins |
| Aug 28 - Sept 6 | Will the torrential rains ever stop? |
| Sept 10-Oct 20 | Finalizing floor framing |
| Nov-Dec | Structural portion of walls, general site maintenance |
| Dec-Jan | Winter break, continuation of wall structure, roof framing. |
| Feb | Roof framing really starts rolling, in addition to site development and beginnings of window framing. |
| March-April | Finish roof framing, Pick up straw bales, construct window framing |
| Apr 26-28 | Finalize prep work for bales, incl. window boxes/frames, structural bracing, bale prep |
| May 4 | THE BIG DAY. Laying the straw bales. See process page for details. |
| May 6-9 | Finishing walls, plastering, whatever else |
| May 10 | Jon, Rob and Brad graduate from Texas A&M |
| May 10- | Apply moisture barrier, wire mesh, stucco. Finish windows, frame patio walls. |